Road Rail Cranes

Bathampton Signal Gantry Recovery BASRE Stage 3 Commissioning

Location: Bathampton

Commisioned by: Alstrom

Date: May 2019

Points of Interest: 

RRC have performed various installation and decommissioning works over the last 3yrs on the Bristol Area Signalling Renewals and Enhancements (BASRE) programme - the biggest recontrol and relock exercise in the UK.
These projects involved final works to transfer from the old to new systems in Bath corridor, relock and recontrol to TVSC. RRC removed a redundant signal gantry - replaced by a gantry which we had previously installed.

RRC performed the Contract Lifts with an AC40 Road Rail Crane accompanied with our innovative T17 lightweight aluminium trailer for mat carriage down to site. All operations were under RRC POS License.

« More case studies